Table of contents
When do you need a permit in Wallonia?
In Wallonia you need an urban planning permit (permis d'urbanisme) in many cases when you place an office unit that is regarded as a building or fixed structure. This is especially the case when the unit stays for a longer time, is connected to utilities or has a clear impact on the site and its surroundings.
Even when the office unit is used for a professional activity, such as administration, reception or staff facilities, the municipality will usually look at the designated use of the plot and the applicable urban planning regulations. For very temporary installations, for example on a building site, exceptions or simplified procedures may exist, but these differ per situation. It is therefore wise to contact the urban planning department of the Walloon municipality where the site is located before installation.
The basis: the Walloon code CoDT
The spatial planning rules in Wallonia are set out in the Code du Développement Territorial (CoDT), which has applied since 1 June 2017 and has been amended several times since. The CoDT determines which actions require an urban planning permit. A separate list covers the works that are exempt from a permit or for which a lighter procedure applies. That list was renewed in 2025.
An exemption applies only if your situation fits that list exactly and you meet all the conditions, for example regarding dimensions, location and duration. If the office unit is not on the list, a permit is needed. The regional plan (plan de secteur) and any local guidelines also determine what is allowed on your plot.
Because the rules in Wallonia differ from those in Flanders, it is wise not to mix the two up. You can read the Flemish rules in placing an office unit in Flanders.
Placing a temporary or permanent office unit
The distinction between a temporary and a permanent office unit is important. A temporary office unit is usually installed for a limited period, for example during renovations, works on a building site or a temporary expansion of activities. In some cases such a temporary installation can be permitted more easily, especially if the unit is completely removed afterwards and the site is restored to its original state.
If, on the other hand, the office unit is used for a longer time, anchored in the ground or integrated into the operations of a business, the municipality will more readily regard it as a permanent structure. In that case stricter rules often apply and an urban planning permit is generally necessary. Sometimes a municipality grants a permit for a fixed period, after which the unit has to go again.

Rules on siting, height and appearance
When placing an office unit in Wallonia you must take into account the siting on the plot, the distance to plot boundaries, the height of the structure and the view towards the surroundings. The municipality will check whether the unit fits within the designated use of the area, for example an industrial zone, agricultural zone, residential area or mixed area. Local plans, subdivision regulations or special urban planning rules can also impose restrictions.
A unit that is visible from the public road, stands close to neighbours or affects the streetscape can more readily be given additional conditions regarding colour, facade cladding, roof shape or landscape integration. It helps to submit a clear site plan, photos and technical data sheets of the office unit with the application. Our office units are 3.2 metres wide, 5.2 to 13.2 metres long and 2.88 metres high (including the roof edge); you put that information in the data sheet.

Connections, safety and accessibility
Besides the urban planning rules, practical and technical regulations also play a role. As soon as the office unit is connected to electricity, water, sewer, internet or heating, this must be done safely and in accordance with the applicable standards. The unit has all connections correctly prepared inside. Connecting to electricity, water and sewer on site is done by a local specialist.
For professional use, fire safety, ventilation, insulation and evacuation options are important points of attention. Our office units have walls and floor with Rc 4.55 and a roof with Rc 5.56. If employees, clients or visitors use the unit, you must also take into account occupational safety and, where applicable, accessibility for people with reduced mobility.
Think, for example, of safe access, a stable subsoil, sufficient lighting, stairs or ramps and clear emergency exits. The municipality or fire brigade may give advice on this or impose additional conditions.
How your application at the Walloon municipality works
An application to place an office unit usually starts at the municipality's urban planning department. There you can have it checked whether your project requires a permit and which documents are needed. Often these are:
- an application form;
- a location sketch and a site plan;
- photos of the existing situation;
- plans or technical information of the unit;
- a description of the use.
Depending on the location and the impact, the municipality may ask other bodies for advice or organise a public inquiry. The processing time differs per file, so start in good time and do not place the office unit before you have clarity. A well-prepared file prevents delays and reduces the risk that you have to modify or remove the unit later.
How long does the decision take?
According to the Walloon authorities, once the file has been declared complete the municipality has 30, 75 or 115 days to decide. Which time limit applies depends on whether a public inquiry, opinions from other bodies or the opinion of the regional delegated official (fonctionnaire délégué) are needed. If the municipality does not decide in time, the file goes to that official. So allow for a few months of preparation and processing.
Conclusion
Anyone who wants to place an office unit in Wallonia would do well to look not only at the practical installation, but also at the urban planning side. The rules depend strongly on the duration, the use, the location and the characteristics of the unit.
By gathering information in advance from the Walloon municipality, putting together a clear file and taking safety and integration into the surroundings into account, you avoid problems afterwards and can use your office unit correctly and without worry. An overview for the whole of Belgium can be found in do you need a permit for an office unit in Belgium? Our office units start from € 15,950 incl. VAT (€ 13,182 excl. VAT); all sizes are on price per size. We also deliver and install in Wallonia and the rest of Belgium. Permit advice is free, also for Belgium, and if you wish we handle the permit application for a fee (price on request).
Curious for more? Watch our videos or make an appointment at our showroom at Hazepad 20 in Breda.