From preparation to installation of the unit
The installation of an office unit starts with good preparation. First it is determined exactly where the unit is to stand and how much space is needed for transport, lifting and access to the unit. Matters such as permits, accessibility of the site and the desired layout of the office space are also looked at.
On that basis a schedule is made, so that delivery and installation can run efficiently. Clear preparation prevents delays and ensures that the unit ends up in the right place straight away.
Which size and layout?
Our office units are 5.2 up to and including 13.2 metres long and 3.2 metres wide. An office unit is as standard an empty unit as an open workspace; a toilet and kitchen are optional. A 5×3 office unit is enough for one or two workstations, while a 10×3 office unit offers space for a small team with a meeting spot. You can find help choosing in which dimensions of office unit you need.
Permit: check first
Whether you need an environmental permit (omgevingsvergunning) depends on the location, the size, the use and how long the unit will stay. A site cabin on or close to a building site, needed for the construction work, is permit-free under the national rules. For an office unit at a business premises or on your own land, the municipality's zoning plan (omgevingsplan) often determines whether it is allowed. First take the free permit check. Our permit advice is free; having the application handled costs € 995.00 incl. VAT (€ 822 excl. VAT).
Determining the right ground and foundation
An office unit must be placed on a solid, level and load-bearing base. Depending on the situation, this can be, for example, on concrete slabs, stabilised slabs, foundation beams or special pad foundations. The choice depends on the weight of the unit, the soil conditions and the period of use.
For temporary placement a simple foundation is often sufficient, while for long-term use more attention is needed for stability and settlement. By assessing the ground properly in advance, the unit stays level and doors, windows and connections function as intended.
You can read more about this in which foundation an office unit needs and can an office unit be placed without a foundation.

Letting transport and lifting go safely
When the location is ready, the office unit is transported to the site by lorry. A crane or lorry-mounted crane is usually used for unloading and placing. Safety is very important here: the lifting zone must be clear, the ground must be suitable for the equipment and only authorised persons may carry out the lifting.
The unit is carefully lifted with lifting straps or chains and placed precisely on the prepared foundation. Good communication between driver, crane operator and spotters prevents damage and ensures safe placement.
Because the units are 3.2 metres wide, this is exceptional transport with an exemption from the RDW (the Dutch vehicle authority). The haulier arranges that. Make sure yourself that there is a clear route on your site and a solid set-up spot for the crane. On a business site it is handy to plan the installation outside the busiest loading and unloading times.
Connecting to electricity, water and sewage
After installation the necessary utilities are connected. Think of electricity, lighting, heating, internet, water and possibly sewage. Not every office unit needs the same connections; this depends on the use. A simple office space often needs only power and a data connection, while a unit with a toilet or pantry also needs water and sewer connections.
All connections inside the unit are correctly ready. Connecting to electricity, water and sewer on site is done by a local specialist, preferably a certified installer, so that everything complies with the applicable safety standards and the unit can be used reliably straight away.
Read on about connecting electricity to an office unit and arranging a water connection.
The final check on site before use
Before the office unit is taken into use, a final check takes place. It is checked whether the unit is level, whether doors and windows close properly and whether all connections work correctly. Safety points are also checked, such as fire extinguishers, emergency lighting, ventilation and any escape routes.
Any small adjustments can then be carried out straight away. Only when everything is in order can the office unit be furnished and used as a temporary or permanent workplace.
Checklist at completion
- Unit is level, doors and windows close smoothly.
- No visible transport damage to facade, roof or window frames.
- Electrics, lighting and any air conditioning work.
- With sanitary facilities: water, drainage and toilet tested.
- Fire extinguisher and escape route are present and clear.

Planning and costs of installation
The delivery time is on average 8 weeks. Installing with the crane usually takes a few hours to one working day; more on that in how long installing an office unit takes. Office units start from € 15,950 incl. VAT (€ 13,182 excl. VAT). Transport, foundation and installation depend on your location: in the quote request you tick what you want us to handle and you receive an indication by email.
Conclusion
Installing an office unit takes more than just transport and a crane. Good preparation, a suitable foundation, safe lifting and correct connections together determine the end result. By carrying out each step carefully, a practical, safe and comfortable office space is created that can be deployed quickly at almost any location.